We have light!
This week Gooch Electric completed our lighting installation and all work requiring their high lift and Ross Allen Flooring has begun their work. GBH installed all the stair treads and risers, the communion rail, and choir screen.
VCT tile has been stacked up against the hard wood nosing to create a barrier for self leveling concrete fill to be applied. This will bring the tile up to the same level as the wood.
Next week we hope to see progress continue on flooring and installation to begin on the main doors.
We will be needing volunteers to assist Gunder Church Furnishings in unloading and assembling pews. Once we get that date scheduled, we will be putting out a sign up form.